Project Renderings

Swipe or use the arrows to view more project images

Construction Progress

Swipe or use the arrows to view more project progress images

In 2025, we will continue our work in Ensenada with renovations to the church building to accommodate the growing congregation. This project focuses on expanding the dining area, adding a second floor, and improving the overall functionality of the space.

This represents a significant opportunity to support the local church community as it grows. Church members who are architects, contractors, and volunteers have contributed detailed planning and coordination to this project.

Budget Summary

Category Amount (USD approx.)
Foundation $277.35
Structure $3,765.27
Electrical $515.29
Walls $2,188.24
Ceilings $823.53
Roofing $2,248.82
Windows and Carpentry $795.00
Total $10,613.51
*USD amounts based on an exchange rate of 1 USD = 17.0 MXN. Rates may vary.

Project Scope

Demolition Work

  • Concrete foundation for isolated footings
  • Chimney
  • Dining area supports
  • Railings/Fences
  • Plywood dining area coverings
  • Relocate gas lines
  • Basketball hoop
  • Kitchen window expansion

Masonry Work

  • Isolated footings (2)
  • Rainwater drainage (1)
  • Sanitary drainage (1)

Structural Work

  • Mezzanine beams
  • Columns
  • Trusses for polycarbonate roofing
  • New metal staircase
  • Removal of existing staircase
  • Handrails

Carpentry Work

  • Mezzanine joists
  • Dining area roof expansion
  • Treatment for existing dining area beams
  • Final roof assembly with plywood and galvanized sheet metal
  • Room partitions
  • Type 1 doors
  • Type 2 wall doors
  • Window frames
  • Cover old staircase opening

Electrical Work

  • Dining area lighting
  • Light switches
  • Dining area wiring
  • Second floor wiring
  • Second floor outlets and switches
  • Second floor lighting
Detailed budget information is shown above in the summary section.